News & Alerts

Church and 9th Closure & Detour Map

On Monday, November 2, Church Avenue will be closed between Sixth Street and Franklin Street. Ninth Avenue between Sixth and Franklin Streets will also be closed. The closures will be in place while the contractor completes underground infrastructure upgrades/improvements, retaining walls, curb and sidewalk, flat work and paving. Both streets are scheduled to be closed for approximately 6 months. See the larger PDF map for full details.

 

Ash and Echols Closed at Fifth

TRAFFIC ALERT

Downtown Links Constructors (DLC), under contract with the City of Tucson Department of Transportation and Mobility have begun work on the Downtown Links project.

Motorists, bicyclists and pedestrians should anticipate intermittent lane restrictions throughout the limits of the project in addition to the following upcoming work:

On Wednesday, October 21, Ash Avenue at Fifth Street closed to vehicular traffic. This temporary restriction will be in place until the sewer bypass system is removed. Removal is scheduled in approximately six weeks. (see map)

On Friday, October 23, the intersection of Fifth Street and Echols Avenue will be closed. The temporary closure is scheduled to be in place for approximately four weeks while a new sewer manhole is installed.
• All vehicle and bicycle travel through the intersection will be restricted.
• Access to businesses and residents will be maintained.
• Some on-street parking near the intersection will be impacted

On Monday, November 2, Church Avenue will be closed between Sixth Street and Franklin Street. Ninth Avenue between Sixth and Franklin streets will also be closed. The closures will be in place while the contractor completes underground infrastructure upgrades/improvements, retaining walls, curb and sidewalk, flat work and paving. Both streets are scheduled to be closed for approximately 6 months.
• All vehicular, pedestrian and bicycle access will be prohibited within the closure area.
• Access to residents and businesses in the area will be maintained.
• Emergency access will be maintained.

The contractor is working on the new drainage infrastructure north of Sixth Street between Stone Avenue and Ninth Avenue.
• Motorists, bicyclists and pedestrians traveling through this area should watch for equipment entering and exiting the work site.

The contractor continues clearing plant material for the future roadway alignment, removing existing fences, walls, and asphalt concrete in various areas throughout the project limits.

The 30-month construction project is scheduled for completion in early 2023.

The schedule is subject to change due to inclement weather or unforeseen circumstances.

The Regional Transportation Authority, a political subdivision of the state and independently governed, has invested more than $1.2 billion in transportation projects and services to improve mobility, safety, economic vitality and quality of life in the region. The RTA collects a half-cent excise (sales) tax from its special taxing district within Pima County to fund its 20-year regional transportation plan. The plan and tax were approved by voters in May 2006. The Downtown Links project is part of the RTA plan and is managed by the City of Tucson. For more information, visit www.RTAmobility.com


ALERTA DE TRÁFICO

Downtown Links Constructors (DLC), bajo contrato con el Departamento de Transporte y Movilidad de la Ciudad de Tucson han comenzado a trabajar en el proyecto Downtown Links.

Los automovilistas, ciclistas y peatones deben anticipar las restricciones de carriles intermitentes a lo largo de los límites del proyecto, además de los siguientes trabajos próximos:

El miércoles 21 de octubre, la Avenida Ash en la Calle Cinco estará cerrada al tráfico.  Esta restricción temporal estará en efecto hasta que se retire el sistema de desvío del alcantarillado. La eliminación está programada en aproximadamente seis semanas. (ver mapa)

El viernes 23 de octubre, la intersección de la Calle Cinco y la Avenida Echols estará cerrada. El cierre temporal está programado para estar en efecto durante aproximadamente cuatro semanas mientras se instala una nueva alcantarilla.

  • Se restringirá el paso de vehículos y bicicletas por la intersección.
  • Se mantendrá el acceso a los negocios.
  • Algunos estacionamientos en la calle cerca de la intersección estarán afectados.

El lunes 2 de noviembre, la Avenida Church estará cerrada entre la Calle Seis y la Calle Franklin. La Avenida Nueve entre las Calles Seis y Franklin también estará cerrada. Los cierres estarán en efecto mientras el contratista completa las actualizaciones/mejoras de la infraestructura subterránea, muros de retención, bordillos y aceras, trabajos de explanación y pavimentación. Está previsto que estas calles esten cerradas durante aproximadamente 6 meses.

  • Se prohibirá el acceso de vehículos, peatones y bicicletas dentro de la zona de cierre.
  • Se mantendrá el acceso a los residentes y negocios de la zona.
  • Se mantendrá el acceso de emergencia.

El contratista está trabajando en la nueva infraestructura de drenaje al norte de la Calle Seis entre la Avenida Stone y la Avenida Nueve.

  • Los automovilistas, ciclistas y peatones que viajen por esta zona deben estar atentos a los equipos que entran y salen del sitio de trabajo.

El contratista sigue limpiando el material vegetal para la futura alineación de la calle, eliminando las cercas, los muros y el concreto asfáltico existentes en varias zonas a lo largo de los límites del proyecto.

Se prevé que el proyecto de construcción, de 30 meses de duración, se termine a principios de 2023.

El programa está sujeto a cambios debido a las inclemencias del tiempo o a circunstancias imprevistas.

La Autoridad Regional de Transporte (RTA), una subdivisión política del estado y gobernada de forma independiente, ha invertido más de $1.2 mil millones de dólares en proyectos y servicios de transporte para mejorar la movilidad, la seguridad, la vitalidad económica y la calidad de vida en la región. La RTA recolecta un impuesto de medio centavo de su distrito fiscal especial dentro del Condado de Pima para financiar su plan de transporte regional de 20 años. El plan y el impuesto fueron aprobados por los votantes en mayo de 2006. El proyecto de Downtown Links es parte del plan de la RTA y es administrado por la Ciudad de Tucson. Para obtener más información, visite www.RTAmobility.com.

Stone and Fifth Avenue Closed Monday

TRAFFIC ALERT

Downtown Links Constructors (DLC), under contract with the City of Tucson Department of Transportation and Mobility have begun work on the Downtown Links project.

Motorists, bicyclists and pedestrians should anticipate intermittent lane restrictions throughout the limits of the project in addition to the following upcoming work:

Stone Avenue will be closed at Fifth Street on Monday, October 19, 2020 from 8 p.m. to 6 a.m. the following morning. This closure will allow the contractor to install a sewer bypass system across Stone Avenue in preparation of new manhole and sewer line installation work.

  • Vehicles and bicycles on Stone Avenue will be detoured around the work area using University Avenue, Sixth Avenue and Sixth Street.

Beginning Monday, October 19, through Friday, October 23, parking along the south side of Fifth Street will not be permitted from Seventh Avenue to Ash Avenue. This parking restriction will be in place while the contractor installs a sewer bypass system.

On Wednesday, October 21, Ash Avenue at Fifth Street will be closed to vehicular traffic. This temporary restriction will be in place until the sewer bypass system is removed. Removal is scheduled in approximately six weeks.

On Friday, October 23, the intersection of Fifth Street and Echols Avenue will be closed. The temporary closure is scheduled to be in place for approximately four-weeks while a new sewer manhole is installed.

  • All vehicle and bicycle travel through the intersection will be restricted.
  • Access to businesses will be maintained.

The contractor is working on the new drainage infrastructure north of Sixth Street between Stone Avenue and Ninth Avenue.

  • Motorists, bicyclists and pedestrians traveling through this area should watch for equipment entering and exiting the work site.

The contractor continues clearing plant material for the future roadway alignment, removing existing fences, walls, and asphalt concrete in various areas throughout the project limits.

The 30-month construction project is scheduled for completion in early 2023.

The schedule is subject to change due to inclement weather or unforeseen circumstances.


The Regional Transportation Authority, a political subdivision of the state and independently governed, has invested more than $1.2 billion in transportation projects and services to improve mobility, safety, economic vitality and quality of life in the region. The RTA collects a half-cent excise (sales) tax from its special taxing district within Pima County to fund its 20-year regional transportation plan. The plan and tax were approved by voters in May 2006. The Downtown Links project is part of the RTA plan and is managed by the City of Tucson. For more information, visit
www.RTAmobility.com


ALERTA DE TRÁFICO

Downtown Links Constructors (DLC), bajo contrato con el Departamento de Transporte y Movilidad de la Ciudad de Tucson han comenzado a trabajar en el proyecto Downtown Links.

Los automovilistas, ciclistas y peatones deben anticipar las restricciones de carriles intermitentes a lo largo de los límites del proyecto, además de los siguientes trabajos próximos:

La Avenida Stone estará cerrada en la Calle Cinco el lunes 19 de octubre de 2020 de 8 p.m. a 6 a.m. del día siguiente. Este cierre permitirá al contratista instalar un sistema de desvío de alcantarillado a través de la Avenida Stone en preparación de un nuevo trabajo de instalación de alcantarillado.

  • Los vehículos y bicicletas que viajen por la Avenida Stone serán desviados alrededor del área de trabajo usando la Avenida University, la Avenida Seis y la Calle Seis.

A partir del lunes 19 de octubre hasta el viernes 23 de octubre, no se permitirá el estacionamiento en el lado sur de la Calle Cinco, desde la Avenida Siete hasta la Avenida Ash. Esta restricción de estacionamiento estará en efecto mientras el contratista instala un sistema de desvío de alcantarillado.

El miércoles 21 de octubre, la Avenida Ash en la Calle Cinco estará cerrada al tráfico vehicular. Esta restricción temporal estará en efecto hasta que se elimine el sistema de desvío del alcantarillado. La eliminación está programada en aproximadamente seis semanas.

El viernes 23 de octubre, la intersección de la Calle Cinco y la Avenida Echols estará cerrada. El cierre temporal está programado para estar en efecto durante aproximadamente cuatro semanas mientras se instala una nueva alcantarilla.

  • Se restringirá el paso de vehículos y bicicletas por la intersección.
  • Se mantendrá el acceso a los negocios.

El contratista está trabajando en la nueva infraestructura de drenaje al norte de la Calle Seis entre la Avenida Stone y la Avenida Nueve.

  • Los automovilistas, ciclistas y peatones que viajen por esta zona deben estar atentos a los equipos que entran y salen del sitio de trabajo.

El contratista sigue limpiando el material vegetal para la futura alineación de la calle, eliminando las cercas, los muros y el concreto asfáltico existentes en varias zonas a lo largo de los límites del proyecto.

Se prevé que el proyecto de construcción, de 30 meses de duración, se termine a principios de 2023.

El programa está sujeto a cambios debido a las inclemencias del tiempo o a circunstancias imprevistas.


La Autoridad Regional de Transporte (RTA), una subdivisión política del estado y gobernada de forma independiente, ha invertido más de $1.2 mil millones de dólares en proyectos y servicios de transporte para mejorar la movilidad, la seguridad, la vitalidad económica y la calidad de vida en la región. La RTA recolecta un impuesto de medio centavo de su distrito fiscal especial dentro del Condado de Pima para financiar su plan de transporte regional de 20 años. El plan y el impuesto fueron aprobados por los votantes en mayo de 2006. El proyecto de Downtown Links es parte del plan de la RTA y es administrado por la Ciudad de Tucson. Para obtener más información, visite www.RTAmobility.com.

6th Ave & 7th Street Intersection Closed Week of October 12th

TRAFFIC ALERT

Downtown Links Constructors (DLC), under contract with the City of Tucson Department of Transportation and Mobility have begun work on the Downtown Links project.

Motorists, bicyclists and pedestrians should anticipate intermittent lane restrictions throughout the limits of the project in addition to the following upcoming work:

The intersection of Sixth Avenue and Seventh Street will be closed from 6 a.m. Monday, October 12, through 5 p.m. Friday, October 16, 2020. The closure will be in place while the contractor removes existing water lines and installs a temporary sewer bypass system across Sixth Avenue. (See map)

  • Only local traffic will be permitted between Sixth and Seventh streets.
  • Vehicle, bicycle and pedestrian access to all businesses on Sixth Avenue between Sixth and Seventh Street will be maintained.
  • Northbound Sixth Avenue will be closed at Toole Avenue. North and southbound travel will not be permitted through the Sixth Avenue underpass.
  • Vehicular travel will not be permitted on Seventh Street between Arizona Avenue and Sixth Avenue.
  • Pedestrian and bicycle access through the Sixth Avenue underpass will be provided along the east side of the roadway/underpass only.
  • Seventh Street, west of the Sixth Avenue intersection is closed to all vehicle, bicycle and pedestrian traffic.
  • Parking will not be permitted along the southside of Seventh Street, between Sixth Avenue and Arizona Avenue while the sewer bypass system is in place. This parking restriction is expected to be in place through December 31, 2020.

The contractor is working on the new drainage infrastructure north of Sixth Street between Ninth Avenue and Echols Avenue.

  • Motorists, bicyclists and pedestrians traveling through this area should watch for equipment entering and exiting the work site.

The contractor continues clearing plant material for the future roadway alignment, removing existing fences, walls, and asphalt concrete in various areas throughout the project limits.

The 30-month construction project is scheduled for completion in early 2023.

The schedule is subject to change due to inclement weather or unforeseen circumstances.

 The Regional Transportation Authority, a political subdivision of the state and independently governed, has invested more than $1.2 billion in transportation projects and services to improve mobility, safety, economic vitality and quality of life in the region. The RTA collects a half-cent excise (sales) tax from its special taxing district within Pima County to fund its 20-year regional transportation plan. The plan and tax were approved by voters in May 2006. The Downtown Links project is part of the RTA plan and is managed by the City of Tucson. For more information, visit www.RTAmobility.com

 


ALERTA DE TRÁFICO

Downtown Links Constructors (DLC), bajo contrato con el Departamento de Transporte y Movilidad de la Ciudad de Tucson han comenzado a trabajar en el proyecto Downtown Links.

Los automovilistas, ciclistas y peatones deben anticipar las restricciones de carriles intermitentes a lo largo de los límites del proyecto, además de los siguientes trabajos próximos:

La intersección de la Avenida Seis y la Calle Siete estará cerrada desde las 6 a.m. del lunes 12 de octubre hasta las 5 p.m. del viernes 16 de octubre de 2020. El cierre se llevará a cabo mientras el contratista elimina las líneas de agua existentes e instala una sistema temporal de desvío de alcantarillado a través de la Avenida Seis. (Vea el mapa)

  • Solamente se permitirá el tráfico local entre las calles Seis y Siete.
  • Se mantendrá el acceso a los vehículos, las bicicletas y los peatones a todos los negocios de la Avenida Seis entre las calles Seis y Siete.
  • La Avenida Seis en dirección hacia el norte estará cerrada en la Avenida Toole. No se permitirá viajar en dirección hacia el norte o sur a través del paso subterráneo de la Avenida Seis.
  • No se permitirá el tránsito vehicular en la Calle Siete entre la Avenida Arizona y la Avenida Seis.
  • Se proporcionará acceso para peatones y ciclistas a través del paso subterráneo de la Avenida Seis a lo largo únicamente del lado este de la calle/el paso subterráneo.
  • La Calle Siete, al oeste de la intersección de la Avenida Seis está cerrada al tráfico de los vehículos, las bicicletas y los peatones.
  • No se permitirá el estacionamiento a lo largo del lado sur de la Calle Siete, entre la Avenida Seis y la Avenida Arizona mientras el sistema de desvío del alcantarillado esté en funcionamiento. Se espera que esta restricción de el estacionamiento esté implementada hasta el 31 de diciembre de 2020.

El contratista está trabajando en la nueva infraestructura de drenaje al norte de la Calle Seis entre la Avenida Nueve y la Avenida Echols.

  • Los automovilistas, ciclistas y peatones que viajen por esta zona deben estar atentos a los equipos que entran y salen del sitio de trabajo.

El contratista sigue limpiando el material vegetal para la futura alineación de la calle, eliminando las cercas, los muros y el concreto asfáltico existentes en varias zonas a lo largo de los límites del proyecto.

Se prevé que el proyecto de construcción, de 30 meses de duración, se termine a principios de 2023.

El programa está sujeto a cambios debido a las inclemencias del tiempo o a circunstancias imprevistas.

 La Autoridad Regional de Transporte (RTA), una subdivisión política del estado y gobernada de forma independiente, ha invertido más de $1.2 mil millones de dólares en proyectos y servicios de transporte para mejorar la movilidad, la seguridad, la vitalidad económica y la calidad de vida en la región. La RTA recolecta un impuesto de medio centavo de su distrito fiscal especial dentro del Condado de Pima para financiar su plan de transporte regional de 20 años. El plan y el impuesto fueron aprobados por los votantes en mayo de 2006. El proyecto de Downtown Links es parte del plan de la RTA y es administrado por la Ciudad de Tucson. Para obtener más información, visite www.RTAmobility.com.

 

Sixth Avenue Restriping Thursday Night

Sixth Avenue, between Sixth Street and Seventh Street, is scheduled to be re-striped beginning at 8 p.m., Thursday, October 8, 2020. The restriping operation will provide back-in parking along the east side of Sixth Avenue and parallel parking along the west side. Sixth Avenue is scheduled to reopen to vehicular travel by 3 a.m. Friday, October 9.

  • Sixth Avenue will be closed to all vehicular travel between Sixth and Seventh streets during the restriping operation.
  • Crews will paint over all conflicting existing stripes and re-stripe new lines with temporary paint, as well as re-paint the existing stop bars and cross walks at the Sixth Avenue and Seventh Street intersection.

The Regional Transportation Authority, a political subdivision of the state and independently governed, has invested more than $1.2 billion in transportation projects and services to improve mobility, safety, economic vitality and quality of life in the region. The RTA collects a half-cent excise (sales) tax from its special taxing district within Pima County to fund its 20-year regional transportation plan. The plan and tax were approved by voters in May 2006. The Downtown Links project is part of the RTA plan and is managed by the City of Tucson. For more information, visit www.RTAmobility.com.


La Avenida Seis, entre la Calle Seis y la Calle Siete, está programada para ser repintada a partir de las 8 p.m. el jueves 8 de octubre de 2020.  La operación de pintar proveerá estacionamientos de respaldo sobre el lado este de la Avenida Seis y estacionamientos paralelos sobre el lado oeste. La Avenida Seis está programada para volver abrir al tráfico a las 3 a.m. el viernes 9 de octubre.

  • La Avenida Seis estará cerrada a todo el tráfico entre las calles Seis y Siete durante la operación de pintar.
  • Los equipos pintarán sobre todas las rayas existentes y volverán a pintar las rayas nuevas con pintura temporal, tambien volverán a pintar las rayas de paradas existentes y los pasos de peatones en la intersección de la Avenida Seis y la Calle Siete.

La Autoridad Regional de Transporte (RTA), una subdivisión política del estado y gobernada de forma independiente, ha invertido más de $1.2 mil millones de dólares en proyectos y servicios de transporte para mejorar la movilidad, la seguridad, la vitalidad económica y la calidad de vida en la región. La RTA recolecta un impuesto de medio centavo de su distrito fiscal especial dentro del Condado de Pima para financiar su plan de transporte regional de 20 años. El plan y el impuesto fueron aprobados por los votantes en mayo de 2006. El proyecto de Downtown Links es parte del plan de la RTA y es administrado por la Ciudad de Tucson. Para obtener más información, visite www.RTAmobility.com.

Initial Concrete Work Begins

TRAFFIC ALERT

Downtown Links Constructors (DLC), under contract with the City of Tucson Department of Transportation and Mobility have begun work on the Downtown Links project.

Motorists, bicyclists and pedestrians should anticipate intermittent lane restrictions throughout the limits of the project in addition to the following upcoming work:

At 11 p.m. Monday, October 5, the contractor will begin initial concrete work for the portion of storm drain installation north of Sixth Street, between Stone and Echols avenues. Work on the storm drain will continue daily for the next several months. Residents, businesses and travelers through the area should expect:

  • Light plants in operation during night work
  • Concrete pumps and trucks entering and exiting the area
  • Large equipment in, and traveling through, the work zone
  • Audible back-up alarms

The contractor continues with the nightly soil export operation from the vacant lot north of Broadway, adjacent to the Aviation Bikeway and West of Iron Horse Park. The soil export operation is expected to continue through mid-October 2020.

The contractor will continue work for new drainage infrastructure in the vacant lot north of Sixth Street between Stone Avenue and Ninth Avenue.

  • Motorists, bicyclists and pedestrians traveling along Sixth Street and/or Stone Avenue in this area should watch for equipment entering and exiting the work site.

The contractor continues clearing plant material for the future roadway alignment, removing existing fences, walls, and asphalt concrete in various areas throughout the project limits.

The 30-month construction project is scheduled for completion in early 2023

The schedule is subject to change due to inclement weather or unforeseen circumstances.

The Regional Transportation Authority is an independent taxing district with a mission to deliver multimodal transportation projects that improve our region’s mobility, safety and environment. The district’s voters approved the 20-year RTA plan in 2006. To date, the RTA has invested over $1.2 billion generated by the RTA’s half-cent excise tax within Pima County to improve your quality of life and support the region’s economic vitality. This project is managed by The City of Tucson. For more information, visit www.RTAmobility.com


ALERTA DE TRÁFICO

Downtown Links Constructors (DLC), bajo contrato con el Departamento de Transporte y Movilidad de la Ciudad de Tucson han comenzado a trabajar en el proyecto Downtown Links.

Los automovilistas, ciclistas y peatones deben anticipar las restricciones de carriles intermitentes a lo largo de los límites del proyecto, además de los siguientes trabajos próximos:

A las 11 p.m. del lunes 5 de octubre, el contratista comenzará el trabajo inicial de concreto para la porción de la instalación del drenaje pluvial al norte de la Calle Seis, entre las avenidas Stone y Echols. El trabajo en el drenaje pluvial continuará diariamente durante los próximos meses. Los residentes, negocios y viajeros de la zona deben esperar:

  • Torres de luces en funcionamiento durante el trabajo nocturno
  • Las máquinas de concreto y los camiones que entran y salen de la zona
  • Grandes equipos en, y viajando a través de, la zona de trabajo
  • Alarmas audibles de seguridad

El contratista continuará con la operación nocturna de exportación de tierra desde el lote vacante al norte de la Broadway Bulevar, adyacente a la Aviation Autopista y al oeste del Parque Iron Horse. Se espera que la operación de exportación de tierra continúe hasta mediados de octubre de 2020.

El contratista continuará trabajando en una nueva infraestructura de drenaje en el lote vacante al norte de la Calle Seis entre la Avenida Stone y la Avenida Nueve.

  • Los automovilistas, ciclistas y peatones que viajen por la Calle Seis y/o la Avenida Stone en esta área deben estar atentos a los grandes equipos que entran y salen del sitio de trabajo.

El contratista sigue limpiando el material vegetal para la futura alineación de la calle, eliminando las cercas, los muros y el concreto asfáltico existentes en varias zonas a lo largo de los límites del proyecto.

Se prevé que el proyecto de construcción, de 30 meses de duración, se termine a principios de 2023.

El programa está sujeto a cambios debido a las inclemencias del tiempo o a circunstancias imprevistas.

La Autoridad Regional de Transporte (RTA) es un distrito fiscal independiente con la misión de llevar a cabo proyectos de transporte multimodal que mejoren la movilidad, la seguridad y el medio ambiente de nuestra región. Los votantes del distrito aprobaron el plan de 20 años del RTA en 2006. Hasta la fecha, el RTA ha invertido más de $1.2 billones generados por el impuesto de medio centavo del RTA dentro del Condado de Pima para mejorar su calidad de vida y apoyar la vitalidad económica de la región. Este proyecto es administrado por la Ciudad de Tucson. Para más información, visite: www.RTAmobility.com