Field Activities for Dec. 16 – 20

Downtown Links Constructors (DLC), under contract with the City of Tucson Transportation Department, continue pre-construction field activities which are scheduled to continue through the end of December 2019. The traveling public will see equipment, work crews and short-term traffic control during this investigative phase of work which includes; surface, subsurface, geotechnical, environmental and survey verifications. The traveling public should anticipate the following traffic closures:

  • On Monday, December 16 and Tuesday, December 17, from 7 a.m. to 3 p.m. each day, parking will not be permitted on north or southbound Seventh Avenue between Sixth and Seventh streets. Access to businesses in the area will be maintained.
  • On Wednesday, December 18, from 7 a.m. to 3 p.m., Arizona Avenue will be closed at the intersection of Seventh Street.
  • On Wednesday, December 18, from 7 a.m. to 3 p.m. westbound Sixth Street will be reduced to one travel lane between Echols and Stone avenues. Access to businesses and turn movements will be maintained.
  • On Thursday, December 19, from 7 a.m. to 3 p.m. northbound Sixth Avenue will be closed between Sixth and Seventh streets.
    • All northbound Sixth Avenue traffic will be required to turn either right or left at Seventh Street.
    • Southbound Sixth Avenue travel will NOT be impacted.
    • Access to businesses will be
  • On Thursday, December 19, from 7 a.m. to 3 p.m. the two-way bike lane along the eastside of Stone Avenue will be closed between Toole Avenue and Council Street. Parking will not be affected.
  • On Friday, December 20, from 7 a.m. to 3 p.m. the sidewalk along the southside of Sixth Street will be closed between Church and Main avenues.
  • During this work, equipment for the pothole operations will be located on Meyer Avenue, south of the neighborhood wall. Access to residents on Meyer Avenue will not be
  • On Friday, December 20, from 10 a.m. to 2 p.m., the outside lane of eastbound 6th Street will be closed at Church Avenue.
  • Right turns from eastbound Sixth Street to southbound Church Avenue will be
  • Right turns from northbound Church Avenue to eastbound Sixth Street will be
  • Left turns from northbound Church Avenue to westbound Sixth Street will NOT be permitted

The schedule is subject to change due to inclement weather or unforeseen circumstances.

The Regional Transportation Authority is an independent taxing district with a mission to deliver multimodal transportation projects that improve our region’s mobility, safety and environment. The district’s voters approved the 20-year RTA plan in 2006. To date, the RTA has invested over $1.2 billion generated by the RTA’s half-cent excise tax within Pima County to improve your quality of life and support the region’s economic vitality. This project is managed by The City of Tucson. For more information, visit www.RTAmobility.com