The contractor is currently constructing the underpass beneath the Union Pacific Railroad (UPRR) west of Stone Avenue.

The shoring operation is complete and UPRR trains have been shifted to the temporary shoefly where they will remain while the contractor begins excavation for the first half of the underpass.

All 48 of the drilled shafts for the underpass have been completed and the contractor is installing the UPRR longline fiber beneath the underpass structure. Once the longline fiber installation is complete, the contractor will begin constructing the underpass bridge abutments.